S3040A Radial Insertion Installation Guide by Southern Machinery
The S3040A is an inline radial insertion system with 40 component stations, made of a radial core machine, two sequencer modules, a PCB loader and a PCB unloader. This installation guide from Southern Machinery turns the manual into a ten-step checklist: unpack, position within a 5 m x 4.5 m footprint, level the core machine first, align both sequencer modules, connect power, air and SMEMA, then align the loader and unloader. Following one sequence reduces rework, protects line uptime and helps THT teams move from delivery to commissioning with fewer surprises. Installation is done by trained technicians or under remote guidance from a Southern Machinery engineer, with global service and spare parts support behind it.
Oct 27, 2026 · Updated Oct 27, 2026 · Southern Machinery

S3040A Radial Insertion Installation Guide | Southern Machinery
What is the S3040A installation guide for? The S3040A is an inline radial insertion system with 40 component stations, built from a radial core machine, two sequencer modules, a loader and an unloader. This guide explains how to unpack, position, level, connect and align those five packages so the machine is ready for commissioning.

Why do most radial insertion startups lose days before the first board runs?
Because the machine arrives in five boxes, and every box depends on the others. The source guide states that installation must be carried out by technicians trained by Southern Machinery, or under remote guidance from a Southern Machinery service engineer.
The hidden problem
Teams plan the floor space for the machine and forget the sequence: core machine first, then everything aligned to it. A module placed before the core is level has to be moved again.
What arrives in the box?
The S3040A ships in five main packages plus accessories.
| Box | Content |
|---|---|
| Box 1 | Radial core machine |
| Box 2 | Radial sequencer module 1 |
| Box 3 | Radial sequencer module 2 |
| Box 4 | PCB loader |
| Box 5 | PCB unloader |
Accessories listed in the source: sequencer chain, scrap bin and tool box, spare parts kit, 10 sets of magazines (2 sets are installed inside the loader and unloader free of charge), an ammo-pack component separator, and ammo-pack component bases (1 per 10 stations, one on each side).
What is a repeatable installation sequence?
Use this ten-step checklist, taken in the order of the guide.
- Unpack and check every module against the box list.
- Position the system. Overall footprint is 5 m x 4.5 m; the minimum working area is 8 m x 7.5 m.
- Remove accessories, transport protection and cable ties; refit the front handle in its working position; remove rear covers.
- Install and level the radial core machine first, then lock the feet.
- Align sequencer module 1 behind the core machine, then module 2 to module 1; level and fix them together.
- Fit and tension the sequencer chain over the sprockets.
- Mount the sequencer push-button box.
- Connect cables and air (details below).
- Install the ammo-pack component bases and separators.
- Align the loader and unloader conveyor rails with the core machine in height and width, level, and lock the feet.
Safety rules that save rework
Keep main power and compressed air disconnected until all modules are positioned, levelled, aligned and fully connected. The core machine and sequencer modules are heavy, so use suitable lifting equipment and enough people. Route cables and air hoses so they cannot be pinched, stretched or walked on.
How should power, air and signals be connected?
- Main power input: single-phase 220 V AC.
- Compressed air: 5 kgf/cm2 (approx. 0.5 MPa).
- Power, air and SMEMA cables run between the core machine and the loader.
- Two air lines (Air 1 and Air 2) go from the core machine to sequencer module 1.
- Match each lettered plug to its labelled socket.
- Three plugs go to the PC at the front of the core machine.
- Connect the chain motor drive cable and the servo drive cables.
- Between module 1 and module 2, all 7 cables must be connected, including the chain drive motor cable.
Check every plug for correct position and full engagement before applying power.
How does it fit into a complete PCB assembly line?
The loader sits on the input side and the unloader on the output side, with SMEMA signalling to the loader. Radial insertion is one stage of a THT flow; see Southern Machinery's THT machine range, wave soldering machines and board handling systems for the stages around it. For mixed lines, ask about inspection equipment too. Southern Machinery was founded in Shenzhen in 2011 and serves 237+ global customers with SMT and THT PCB assembly automation.
What is the cost of getting installation wrong?
Install time is lost on rework, not on lifting. A simple planning formula:
Installation rework cost = rework hours x (crew rate + idle line cost per hour)
Example only, depending on configuration and subject to final technical confirmation: if a misaligned module costs 6 hours of rework for a crew of 3, the loss is 6 x 3 = 18 labour-hours plus the idle line time. The source gives no installation-time figures; contact Southern Machinery to confirm.
Selection and site checklist
| Item | Value from source |
|---|---|
| Stations | 40 |
| System footprint | 5 m x 4.5 m |
| Minimum working area | 8 m x 7.5 m |
| Power | 1-phase 220 V AC |
| Air supply | 5 kgf/cm2 (approx. 0.5 MPa) |
| Magazines | 10 sets supplied |
| Module cables (1 to 2) | 7 |
FAQ
What does the S3040A system include? A radial core machine, two sequencer modules, a PCB loader and a PCB unloader, plus accessories.
Who should install it? Technicians trained by Southern Machinery, or under remote guidance of a Southern Machinery service engineer.
How much floor space is needed? Footprint 5 m x 4.5 m; minimum working area 8 m x 7.5 m.
What air pressure is required? 5 kgf/cm2 (approx. 0.5 MPa).
What do I quote for service? The model (S3040A) and the serial number.
Keep this checklist, then go to start-up
Save the ten steps for your next line move or audit. Next in the series: the S3040 operation manual covers start-up and commissioning after installation is complete.
Ready to plan your line? Request a quote or contact Southern Machinery at info@SMThelp.com. More documents: file.autoinsertion.com.
Comments